University Hospitals Bristol and Weston NHS Foundation Trust
Ward D703, Haematology and Bone Marrow Transplant Unit
- Client
- University Hospitals Bristol and Weston NHS Foundation Trust
- Location
- Bristol Haematology and Oncology Centre
- Value
- £277,000
- Programme
- 10 weeks
- Sector
- Healthcare
The Ward D703 project was meticulously executed within the sensitive environment of Bristol's Haematology and Oncology Centre. The refurbishment took place on level 7 and required stringent control measures to prevent construction dust and debris from affecting the main ward.
D703 is known for its comprehensive care for patients with blood-related cancers such as leukaemia, lymphoma and myeloma, as well as non-malignant haematological conditions like sickle cell disease.
Scope
- Deconstruction of existing partition walls
- Mechanical and electrical alterations and installations, including medical gases
- Construction of new partition walls
- Installation of a suspended ceiling
- Comprehensive decoration works
- Installation of floor coverings
- Fitting of fixtures to provide additional bed space and isolation rooms
Controlling dust and debris
Maintaining a sterile environment in a healthcare setting, particularly in an oncology ward, is paramount. The primary challenge was to control construction dust and debris, ensuring they did not infiltrate the main ward areas. This was achieved through high-efficiency filtration and sealed separation, maintaining the comfort of both patients and staff throughout the refurbishment.
Patient and staff safety
Given the vulnerability of the patients within D703, strict health and safety protocols were adhered to. This included scheduling noisy or disruptive work during off-peak hours and maintaining a clear communication channel with ward staff to minimise any disruption to patient care.
Time management
The project was completed within a tight 10-week programme. Detailed planning and efficient coordination were vital to ensure all tasks were completed on time without compromising the quality of work. Regular progress meetings and a robust project management framework kept the project on track.
Outcome
The new partition walls, suspended ceiling and enhanced fixtures and fittings have provided additional bed space and designated isolation rooms, contributing to better patient care and operational efficiency.
The Trust expressed their satisfaction with the project, particularly commending the team's ability to work within the sensitive ward environment without causing significant disruption, and highlighted the importance of the new facilities in supporting their ongoing commitment to patients with haematological conditions.